← Back to Document LibraryOperations Risk Register Guideline
Contents & downloads
- QHSE-MAN-001
- QHSE-PRO-001
Nomenclature
| Term | Definition |
|---|---|
| WL Risk Matrix | The Westlink 5x5 risk-assessment matrix, which rates a risk by combining its likelihood with the consequence (severity) of its worst credible outcome. |
| Likelihood | How probable it is that a risk event occurs, expressed on the five-level scale Highly Unlikely to Highly Likely. |
| Consequence | The severity of the worst credible outcome of a risk event, expressed on the five-level scale Insignificant (1) to Severe (5). |
| Residual Risk | The risk rating that remains after the current controls have been applied. |
| Risk Register | A record of identified risks, their assessment and their controls. Live project and operational risk registers are maintained in project documentation and in the isCompliant platform; they are not controlled WMS documents and carry no WMS document code. |
| WMS | Westlink Management System. |
Purpose
This guideline gives the operations and projects department a consistent method for identifying, assessing and recording operational risk. It establishes the Westlink (WL) risk matrix and risk-rating method and the contexts in which risk registers are developed. It also sets out the operational risk themes across the department’s activity groups. Applying it lets the department develop project and tender risk registers on a common basis. It also helps capture ongoing operational risks and their mitigation strategies.
Scope
This guideline applies to the operations and projects department. It is an overarching guideline that informs individual project and tender risk registers; it is not itself a live risk register. Live project and operational risk registers, and incident, hazard and corrective-action records, are maintained in project documentation and in the isCompliant platform — this guideline informs them but does not reproduce them.
Definitions
Terms and acronyms used in this document are defined in the Nomenclature table at the front of this document.
Risk Assessment Method
Each risk is rated with the WL risk matrix by combining its likelihood with the consequence (severity) of its worst credible outcome. A risk is rated both inherently and as a residual risk after current controls have been applied. The likelihood and consequence scales are set out below, followed by the risk matrix that combines them.
Likelihood
Likelihood is assessed on the following five-level scale, with the indicative frequency used as a guide.
| Likelihood | Indicative frequency |
|---|---|
| Highly Likely | Likely to occur within a 1 year period. |
| Likely | Likely to occur within a 1 – 5 year period. |
| Probable | Likely to occur within a 5 – 20 year period. |
| Unlikely | Likely to occur within a 20 – 50 year period. |
| Highly Unlikely | Not likely to occur within a 50 year period. |
Consequence
Consequence is assessed on the following five-level scale against the worst credible outcome, considering health and safety, environment, community and human rights, and company reputation, legal and commercial impacts.
| Level | Descriptor |
|---|---|
| Severe (5) | 6 or more fatalities or 6 or more life shortening illnesses; or severe impact to the environment where recovery of ecosystem function takes 10 years or more; or severe impact on community lasting more than 12 months or a substantiated human rights violation impacting 6 or more people; or severe impact on company reputation, investment attractiveness, legal rights or compliance, social value proposition or ability to access opportunities at a global level. |
| Major (4) | 1-5 fatalities or 1-5 life shortening illnesses; or serious impact to the environment, where recovery of ecosystem function takes between 3 and up to 10 years; or serious impact on community lasting 6-12 months or a substantiated human rights violation impacting 1-5 persons; or serious impact on company reputation, investment attractiveness, legal rights or compliance, social value proposition or ability to access opportunities at a national level. |
| Moderate (3) | Life altering or long term/permanent disabling injury or illness to one or more persons; or substantial impact to the environment, where recovery of ecosystem function takes between 1 and up to 3 years; or substantial impact on community lasting 2-6 months; or substantial impact on company reputation, legal rights or compliance, social value proposition, or ability to access opportunities at a sub national level (state, territory, province). |
| Minor (2) | Non-life altering or short-term disabling injury or illness to one or more persons; or measurable but limited impact to the environment, where recovery of ecosystem function takes less than 1 year; or measurable but limited community impact lasting less than one month; or measurable but limited impact on company reputation, legal rights or compliance, or social value proposition at a local level (region, city, town). |
| Insignificant (1) | Low level impact resulting in first aid only; or minor, temporary impact to the environment, where the ecosystem recovers with little intervention; or minor, temporary community impact that recovers with little intervention; or minor, temporary impact on company reputation, legal rights or compliance, or social value proposition. |
Risk Rating
The risk rating is read from the WL risk matrix at the intersection of the assessed likelihood and consequence. The same matrix is used to rate the inherent risk and, after controls, the residual risk.
| Likelihood | Insignificant (1) | Minor (2) | Moderate (3) | Major (4) | Severe (5) |
|---|---|---|---|---|---|
| Highly Likely | Medium | High | Very High | Very High | Very High |
| Likely | Medium | High | High | Very High | Very High |
| Probable | Low | Medium | High | High | Very High |
| Unlikely | Low | Low | Medium | Medium | High |
| Highly Unlikely | Low | Low | Low | Low | Medium |
Risk Register Types
Operational risk registers are developed through two workshop contexts. Each workshop uses the WL risk matrix above to rate the identified risks and draws on the operational risk themes and the reference in Appendix A as a prompt for hazard identification.
-
Project Risk Workshop — conducted for an awarded project, producing the project risk register that governs execution.
-
Tender Risk Workshop — conducted during tendering, assessing the risk of a prospective scope before commitment.
Operational Risk Themes
The department’s operational risk falls into five activity-group themes. The themes below summarise the character of the risk in each group; the full point-in-time reference of hazards, risk events and controls is reproduced in Appendix A as a prompt for risk-register development.
Port Operations
Vessel discharge and laydown operations at port: coordination with stevedores, port authority and subcontractors; lifting and crane operations (hooking on/off, rigging); manual handling; vehicle and equipment interaction with personnel in the loading zone; loadout sequencing; and port access and induction compliance.
General
Cross-cutting operational risks: schedule and travel management; correct use of Stop Work Authority; awareness of risks created by other parties on shared sites; and exposure to extreme weather, heat and environmental conditions.
Transport / Heavy Haulage
Road transport and heavy haulage of project cargo: route and road-condition management; vehicle, structure and object interaction; load structural integrity and load restraint; emergency braking and convoy travel; mechanical reliability; and Chain of Responsibility and fatigue-management compliance.
Site Operations
Project-site execution: mobilisation and site access; ground suitability for overmass cargo and crane set-up; simultaneous operations; truck and equipment interactions; suitability of offloading equipment; and coordination of operating times, laydown sequence, equipment and labour with the client.
Contractor Management
Engagement and oversight of subcontractors: prequalification; insurance adequacy; agreement of purchase-order terms and conditions; equipment and labour availability; equipment registration and compliance; and fatigue management of contracted personnel.
Roles and Responsibilities
The roles below carry the main accountabilities for applying this guideline. They reflect the duties already described in this document and in the Appendix A controls; project-specific delegations may assign them differently for a given scope.
| Role | Responsibility | When |
|---|---|---|
| Project Manager | Convenes the Project Risk Workshop, owns the resulting project risk register, and approves residual risk ratings. Ensures contractor prequalification and insurance adequacy before work commences. | On project award and through delivery. |
| Operations Coordinator | Convenes the Tender Risk Workshop and supports the Project Manager with documentation, contractor queries, and confirming labour and equipment availability for operations. | During tendering and operational planning. |
| Supervisor / Line Manager | Applies the WL risk matrix to rate hazards in the field, resolves concerns raised under Stop Work Authority, and maintains and reviews the live register through delivery. | During operations on site. |
Applying This Guideline
This guideline is an overarching reference; it does not replace a project- or tender-specific risk register. To apply it:
-
Run the applicable risk workshop (Project or Tender).
-
Identify the hazards and risk events for the scope, using the activity-group themes and Appendix A as a prompt.
-
Rate each risk with the WL risk matrix (likelihood x consequence), both inherently and as a residual risk after controls.
-
Record the assessed risks, controls and residual ratings in the project or tender risk register.
-
Maintain and review that register through delivery.
Register separation: live project and operational risk registers — and incident, hazard and corrective-action records — are maintained in project documentation and in the isCompliant platform. This guideline informs those registers; it does not reproduce them and carries no live risk data.
Compliance coverage — cited by 2 requirements across 1 framework
ISO 45001:2018(2)
| Requirement | Clause | Coverage | Severity | Notes |
|---|---|---|---|---|
| ISO45001-2018-6.1.2.2-01 | 6.1.2.2 | Partial | §Risk Rating / Activity themesProcess to assess OH&S risks from identified hazards taking existing-control effectiveness into account (residual rating). | |
| ISO45001-2018-6.1.2.2-02 | 6.1.2.2 | Partial | §Risk Assessment Method / Likelihood / ConsequenceDefines the OH&S risk-assessment methodology and criteria — 5x5 matrix, likelihood/consequence scales (incl. H&S), inherent-vs-residual. |
Declared compliance references (2)
ISO45001-2018-6.1.2.2-01ISO45001-2018-6.1.2.2-02
Document Revision Summary
| Rev | Issued | Document Ref | Document Title | Author | Approved |
|---|---|---|---|---|---|
| 1 | 2026-06-16 | OPS-GDL-001 | Operations Risk Register Guideline | FTM (CF) | John A. Di Giovanni |
Document Revision Details
| Rev | Purpose of revision and changes made |
|---|---|
| 1 | Initial issue in new WMS. Reformatted from legacy WLK-GBL-OPS-GDL-001 Operations Risk Register (rev 0, 25/09/2025; an Excel workbook). Re-authored to the WMS Guideline structure: the WL risk matrix and likelihood/consequence scales as the risk-assessment method, the two risk-workshop contexts, the five activity-group risk themes, and the legacy register's 33 risk rows reproduced as a point-in-time reference appendix. Cross-references updated to current WMS codes. Coverage-neutral (orphan). |