    TermDefinition
    ASLApproved Supplier List — the register of suppliers and subcontractors approved for engagement, including approval status and any conditions.
    PMProject Manager — the owner of the project requiring the supplier.
    PQQPrequalification Questionnaire — the standardised questionnaire issued to a potential supplier.
    WMSWestlink Management System.

    Purpose

    This document maps the process for prequalifying a major supplier or subcontractor before engagement. Major-tier prequalification assesses a supplier’s QHSE, technical and financial capability. This assurance ensures externally provided processes, products and services do not adversely affect Westlink’s ability to deliver conforming services to its clients.

    Scope

    This process applies to the prequalification of suppliers and subcontractors for major work scopes. Suppliers for minor works below the major threshold are prequalified under the proportionate minor-tier process (GOV-PRO-005). QHSE-PRO-002 sets out the requirements for ongoing supplier and subcontractor management. These cover evaluation criteria, audit, performance measurement and the Supplier Code of Conduct.

    Canonical Interactive Version

    The canonical, interactive version of this process is the flowchart published on the Westlink intranet at /wms/process-overview (Rev 2). This document is the controlled text representation of that flowchart. If this document and the interactive flowchart ever differ, the flowchart prevails and this document must be updated.

    Definitions

    Terms and acronyms used in this document are defined in the Nomenclature table at the front of this document.

    Roles and Responsibilities

    The process map assigns steps to six lanes.

    RoleResponsibilityWhen
    Project ManagerIdentifies the supplier requirement.Requirement and ASL Check
    ProcurementRuns the prequalification, maintains the ASL and notifies outcomes.Throughout — from PQQ issue to ASL registration and outcome notification
    QHSEConducts the capability assessment and the periodic review.Prequalification and Capability Reviews; Periodic Review
    TechnicalConducts the capability review.Prequalification and Capability Reviews
    FinanceConducts the financial standing check.Prequalification and Capability Reviews
    Senior ManagementMakes the approval decision.Approval Decision

    Process Steps

    Requirement and ASL Check

    • Identify Supplier Requirement (Project Manager) — define the scope and type of supplier or subcontractor needed.

    • Decision: On the Approved Supplier List? (Procurement) — check whether a suitable supplier already exists on the ASL.

    • Yes — select the supplier from the ASL. The prequalification process ends.

    • No — proceed to prequalification.

    Prequalification and Capability Reviews

    • Issue Prequalification Questionnaire (Procurement) — send the standardised PQQ to the potential supplier.

    • Receive Supplier Response (Procurement).

    On receipt of the supplier’s response, three capability reviews are conducted in parallel:

    • QHSE Capability Assessment (QHSE) — review the supplier’s WHS management system, environmental compliance and quality certifications (see QHSE-PRO-001).

    • Technical Capability Review (Technical) — assess technical competence, equipment and experience.

    • Financial Standing Check (Finance) — credit check and financial viability assessment.

    • Compile Assessment Report (Procurement) — consolidate all review findings into a single assessment.

    Approval Decision

    • Decision: Approved? (Senior Management) — senior management decides on supplier approval based on the Assessment Report.

    • No — notify the supplier that it has not been approved. The process ends.

    • Yes — proceed to the conditions decision.

    • Decision: Conditions Required? (Senior Management) — determine whether the approval is subject to conditions.

    • Yes — Procurement sets the conditions and timeframes before the supplier is added to the ASL.

    • No — the supplier is added to the ASL without conditions.

    Registration, Notification and Periodic Review

    • Add to Approved Supplier List (Procurement) — register the supplier on the ASL with its approval status and any conditions.

    • Notify Supplier of Outcome (Procurement).

    • Schedule Periodic Review (QHSE) — set the review date for ongoing supplier performance monitoring. The process ends.

    John A. Di Giovanni
    Chief Executive Officer
    Date:
    12/06/2026
    Compliance coverage — cited by 4 requirements across 2 frameworks

    ISO 9001:2015(3)

    RequirementClauseCoverageSeverityNotes
    ISO9001-2015-8.4.1-028.4.1PartialMediumSupplier Prequalification — Major: prequalification questionnaire + QHSE/technical/financial capability assessment determine the controls applied to each major external provider.
    ISO9001-2015-8.4.2-018.4.2FullSupplier Prequalification — Major: QHSE Capability Assessment, Technical Capability Review and Financial Standing Check before approval ensure external providers do not adversely affect Westlink's delivery of conforming services.
    ISO9001-2015-8.4.2-028.4.2PartialMediumSupplier Prequalification — Major: Assessment Report + approval gate define the controls applied to the provider and the output; the Scheduled Periodic Review determines ongoing verification activity.

    JOSCAR-AU 2026(1)

    RequirementClauseCoverageSeverityNotes
    JOSCAR-Q2.10.1Q2.10.1FullSupplier Prequalification — Major: live documented assessment procedure (questionnaire, QHSE/technical/financial assessment, approval with conditions, periodic review).
    Declared compliance references (4)
    • ISO9001-2015-8.4.1-02
    • ISO9001-2015-8.4.2-01
    • ISO9001-2015-8.4.2-02
    • JOSCAR-Q2.10.1
    Document Revision Summary
    Rev Issued Document Ref Document Title Author Approved
    2 2026-03-12 GOV-PRO-003 Supplier Prequalification — Major FTM (CF) John A. Di Giovanni
    3 2026-06-12 GOV-PRO-003 Supplier Prequalification — Major FTM (CF) John A. Di Giovanni
    Document Revision Details
    Rev Purpose of revision and changes made
    2 Library metadata + compliance-traceability entry for the live interactive process map.
    3 Re-scoped (Phase 3d): controlled text representation of the Rev 2 interactive process map; references updated to WMS codes; legacy restatement removed.
    GOV-PRO-003 Rev 3 — Supplier Prequalification — Major Uncontrolled when printed